Our Zion Building Committee has been meeting regularly to keep the new School Building Project moving along, including:
Contracted with Architect Groth Design Group, approved and signed by Church Council, to begin final drawings
Contracted with civil engineer JB Site Design and structural engineer Core4 Engineering to work with Groth Design Group on the project
Met with Groth Design Group on Sept. 12 for a progress update where slight modifications for Phase 1 and 2 floor plans were discussed to better serve the school mission – these PDFs are posted to the Zion website
A Land Surveyor was recently on-site to develop the grading and final site plan
Architect Todd Dvorak met with the city of Columbus to discuss our site plan and permitting process
Set up monthly progress meetings with the architect. Our next meeting is on Oct. 8
A Zion Interior Design Subcommittee was formed and have met with the interior designer at Groth Design Group
Preliminary schedule for Phase 1:
Architectural plans completed by Thanksgiving
Submit for Bidding and Permitting in December
Construction to begin April 2025 with a 9-month construction timeline
Building Committee: Matt Huber and Mike Uttech, co-charmen, Chad Grambsch, Aaron Larson, and Matt Yaroch